Client: Castleoak
Project: Castleview, Windsor
Scope of Works
Brown field site
8-week demolition of old Windsor Squash Club & other structures on site
Removal of all vegetation
Removal of old Thames water sewer through site
Construction 2 no RC Frames for Care Home & close care blocks 4 & 5 storeys, one with basement including;
Install sheet piled cofferdam to basement
Bulk dig excavation 7000m3
CFA bearing piles throughout
Basement construction/waterproof structure
Underground draining & hard & soft landscaping
Key Points
Design of cantilevered sheet piled cofferdam un-propped
Working adjacent to live Thames water sewer
Zero vibration techniques adopted to sheet pile installation
Continuous movement monitoring of the sheet piles and Thames water sewer during the construction works
Duration
52 weeks (September 2016 – September 2017)
Contract Value:
£7.3M
More Construction Projects Completed by Knockmoy
Let’s Work Together.
Call us now on (+44) 07786 086250
We look forward to hearing from you.